APPENDIX

Appendix 4: Production of the TumenNET
Transboundary Diagnostic Analysis

Process
The Russian lead agent is the overall manager for the production of the TDA.

Local task managers will be responsible for the analytical process in their respective zone. A high level advisory team will provide technical, scientific and programming support as required. The lead agent is responsible for overall quality control.

National authors will be primarily responsible for the preparation of the analyses (causal-chain/socio-economic-political/stakeholder) required for the TDA.

Zonal task managers will compile national inputs into a draft Zonal TDA. They will oversee national stakeholder workshops, managed and coordinated by National SAP planning units

The regional lead agent will supervise that process and compile the 4 zonal TDAs into one comprehensive TumenNET TDA. The LA will provide consulting advice to the zonal task managers to ensure internal consisteny. The LA will also be responsible for quality control (verifying technical accuracy)

The PCU will provide resources, ensure overall coordination, and interface with all parties as and when required and throughout the production phase.

Timeline
Fri 31 Aug TDA policy workshop in Vladivostok
- cluster analyses, gap analysis and prioritization
- constraints identification
- stakeholder analysis

Sat 1 Sep TDA technical meeting in Vladivostok
- refresher training in analytical techniques provided
- TDA outline agreed
- management structure for production of TDA agreed
- writing assignments agreed

Sep 3-28 Step 1 National authors prepare causal-chain analyses for the priority issues identified at the regional TDA workshop and identify underlying root causes
Step 2 National authors prepare socio-economic-political analyses for the root causes identified in step1
Step 3 National authors complete targeted stakeholder analyses basedon findings from the working groups at the regional TDA workshop and based on steps 1 and 2
Sep 25 Mongolian co-authors meeting in Ulaanbaatar
Chinese National Day Holidays before and after October 1
Mon 8 Oct Final deadline for national authors to submit analyses to task managers
Oct 9-20 Task managers compile data from national authors into a draft zonal TDA and prepare a summary document for presentation at stakeholder workshop.
- Lead Agent advisers work for one week with task managers to ensure internal consistency
Oct 21-30 Task managers present draft zonal TDAs to stakeholder workshops in each of the four zones and seek input/comments from the wider local community-involve media.
- Zonal workshop in Seoul will focus on private sector
Nov 1-5 Task managers revise the draft Zonal TDA and incorporate stakeholder feedback.

Tue 6 Nov Task managers submit final Zonal TDA to lead agent in Vladivostok
Nov 7-21 Lead agent compiles Zonal TDAs into one comprehensive TumenNET TDA and checks accuracy of data
Wed Nov 21 Lead agent submits Regional TDA to national Governments for clearance
Nov 21-Dec 14 National Governments clear TDA

Fri Dec 14 Final deadline for national governments to clear TDA to PCU
>Dec 15 Final editing, including language, printing, translation and dissemination